Richboro Sidewalk Project (Phase II)
Project Summary
This project is an extension of the Phase 1 Sidewalk Project completed along 2nd Street Pike in 2022 with a $500,000 grant from the PennDOT Multi-Modal Program. Phase 2 will extend sidewalks along Temperance Lane, Bustleton Pike, Tanyard Road, and Almshouse Road that will connect with existing sidewalks in neighboring developments.
The Township received a $988,000 grant to construct Phase 2 of the plan. The estimated bid date for this project is October 2025, with construction completed in 2026. The estimated construction cost is $988,000. The Township will fund design and construction inspection services of $115,000.